Embankment reinforcement works on the section from 2 km to 5 km of the state-importance regional road No. 206

Project title

Technical working project for embankment reinforcement works on the section from 2.425 km to 5.820 km of the state-importance regional road No. 206 Šilutė–Rusnė

Completed projects
Projektavimas ir rangos darbai
Construction type
Rekonstravimas
Project Location
Rusnė Šilutės r. sav.
Builder
Via Lietuva
fegda group companies
Fegda, Tilsta, SRP projektas
Completed
2019
Parameters
Road length: approximately 2.8 km | Road embankment reinforced using 14,556 driven piles (⌀270) and an equal number of pile caps | 139,740 m² of geosynthetic materials used

Due to challenging geological conditions, it was decided to reinforce the road embankment to ensure long-term stability and safe traffic. The works included the installation of driven piles with pile caps, the placement of a frost-resistant material layer, and the strengthening of the road structure using geosynthetic materials. These solutions improved the durability of the road, reduced the risk of deformation, and ensured reliable connectivity along this section.